(10.2.2015) Completed work at Đale

In February 2015 the first phase of the turbine governor replacement was completed at the hydro power plant Đale near Trilj. Electric and hydraulic control part of the turbine governing system was replaced at the unit A, with the goal to modernize the system and ensure its function in the coming exploitation period.  A new control cubicle of the turbine governing system was  installed, as well as new hydraulic control blocks for the wicket gates and the runner blades, with transition to the proportional control technology. Installation of the modern digital system of position measurement for the wicket gates and the runner blades and modern control software enabled power increase of 1.5 MW per power unit when compared with the existing state. Continued work at the unit B is scheduled for the summer of 2015.

The customer is HEP Proizvodnja d.o.o.